What's
Happening Now
What's Happening Now - February 17, 2021
February 17th, 2021
Crews are working on adding storm sewer systems and placing crushed aggregate base at the Springhill Ave. intersection. Crews are doing more work on housekeeping as...
What's Happening Now - February 10, 2021
February 10th, 2021
Construction crews are have finished landscaping the center of the roundabout. The center ring and the truck apron have also been completed....
What's Happening Now - February 4, 2021
February 4th, 2021
Crews are working to install all new utilities along Broad Street. Before utilities can be completed, conduits must be installed. A conduit is plastic piping that...
What's Happening Now - November 30, 2020
November 30th, 2020
Crews place new storm sewer lines in the proper alignment for a new junction box. ...
What's Happening Now - November 18, 2020
November 18th, 2020
Construction crews are building up what will be the center of the roundabout. Borrow, or filler material, has been hauled in and compacted bringing this part of the...
What's Happening Now - November 4, 2020
November 4th, 2020
Crews use the “Jack & Bore” process to install a 24” waterline at Springhill Avenue. Pipe boring is the method of installing pipes,...
Bike lanes are coming to Broad Street.
October 21st, 2020
This is a look at the progress being made along N. Broad Street. Soon bicyclists in the City of Mobile will have a safe place to ride when traveling along Broad...
What's Happening Now - October 21, 2020
October 21st, 2020
Crews place a new waterline in a trench along N. Broad Street....
What's Happening Now - October 14, 2020
October 14th, 2020
These big green “things” are erosion control domes. They are placed over open inlet or junctions boxes to prevent dirt from getting into the storm sewer...
What's Happening Now - October 7, 2020
October 7th, 2020
At Canal and South Broad Streets, crews discovered a portion of a railbed that was used by the City of Mobile’s trolly system that has since been phased out by...